You can use RTE = FNNESB where NN is your date type in 0041. The documentation from SAP is shown below. Hope this helps.

 

          F          Fixed indicator for deadline calculation

           aa           Date type: Start date of period to be
                        calculated; if the date type is not 'nn,'
                        the second position is left blank.

             e          Unit, in which the duration is calculated:
                        T = days
                        W = week
                        M = months
                        C = complete months
                        K = complete calendar months
                        N = complete calendar months (rounded up)
                        J = Years
                        Y = Complete years
                       The difference between the individual
                       units is explained in

     Calculation Examples
                       in more detail.

              s         End date of period to be calculated:
                        (blank)  End of current payroll period
                        J        End of current calendar year
                        A        Start of current calendar year
                        B        Start of WPBP period
                       No other specifications are possible.

               b        If the date type specified in parameter aa
                        does not exist for the person in question,

Based on the return value you can do your calculations.

 