Re: Work Order component de-allocation in co02?

$
0
0

Hi there,

I need the required qty to still be available for the purchasers to see and fulfill, i just want the confirmation removed so it's available for another priority order..

scenario

work order has 50 confirmed components - we only have 50 in stuck

a priority work order comes in and requires 50.

we need to unconfirm the components from the first work order so that they can be confirmed to the second work order, but we still need to show the requirement of 50 on the first work order for the material planners..

hope this makes more sense!

thanks!

b