Hi team
I have created finished goods material 'FG1'. And I have created the BOM with usage 5(sales and distribution). And in this BOM, I have assigned two raw materials namely RAW1 and RAW2. And I have created for FG1 material for 100 quantity. Now I have run MRP in MD02. After MRP run, I am expecting that, for BOM components (RAW1 and RAW2), PR will be created as result of MRP.
But has not created the PR. Can anyone please explain the reason?
Thanks