Re: operation start time in production order

$
0
0

Hari,

If there is no issue with having op 30 start before or after op 20 is completed, make 20 and 30 parallel, and add a 2 hour setup to 30.

 

If 20 must be completed before 30 is started, then that means that 20 MUST take 2 hours.  Change the duration to a fixed time.

 

Best Regards,

DB49